Renovation Update

As we head towards the first day of school I’m excited with all the things we have managed to accomplish this summer.  We have completed over 90% of the work planned for the summer. A list of the items we have completed can be found at the end of the article.  

 

Upon entering the building, especially in the elementary, you will notice that we do not have all of the items hung back on the walls.  Our first priorities were ensuring the classroom materials were returned to classrooms, the bathrooms were functional, and the cafeteria was able to serve students.  We will continue to work in the evenings and on weekends to hang bulletin boards, coat hooks, etc.

 

One other large item that is unfinished is a portion of the sidewalk in front of the elementary building and the awning.  A portion of the sidewalk will be poured Monday morning, but the crew will continue to work on the awning throughout the week.  Please be patient with the interruption in traffic that this will cause and we urge you to use caution when entering the front parking lot.  Please ensure that you and your child(ren) do not enter the construction areas.

 

Throughout the summer we have encountered a few issues and have managed to resolve them in a timely and satisfactory manner.  We have also found ourselves saying “I wish we had…” As with any project there are items that we “missed” when planning the project.  We have had to remind ourselves that not every item that we wanted to complete could be accomplished within the budget, and thus we have already started our list of other things that we hope to accomplish in the future.

 

Thank you for your continued support of the Green City R-1 School District.  We are so very excited to start the 2019-2020 school year and are ready to welcome our students back.

 

Completed Items

  • Removal of asbestos throughout the school building

  • Replacement of floor tile in all elementary classrooms, the cafeteria/kitchen, HS Science room, hallways, and around the gym floor

  • Replacement of carpet in the band room and the elementary office

  • Replacement of ceiling tiles in elementary classrooms and hallways

  • Additional electrical outlets added to elementary classrooms

  • Replacement of fire alarm system

  • Replacement of security camera system

  • Replacement of the phone system

  • Installation/Replacement of HVAC in the elementary classrooms, business room, kitchen, cafeteria, locker rooms, and gymnasium

  • Replacement of all cabinets in elementary classrooms

  • New epoxy flooring and paint in the elementary bathrooms and bathrooms near the gymnasium, as well as in kitchen and locker rooms

  • Replacement of siding around the elementary

  • Replacement of windows in the elementary

  • Renovation of the elementary office (replacement of walls, doors, countertop/window)